CWTP Wastewater Critical Electrical & Control Spares for Increased Resilience

Purchase of critical electrical, instrumentation and controls spares to increase the resilience of CWTP treatment plant operations.

This is a $540K water & waste project across Christchurch, currently planned.

Why This Project Matters

Reliable wastewater infrastructure protects public health and the environment. This project is part of the council's long-term programme to maintain and upgrade the below-ground network serving all Christchurch residents.

Latest Update

Approved and scheduled for delivery within the Long Term Plan 2024–2034 period.

Budget Details

DetailValue
Total Budget$540K
CategoryWater & Waste
WardCitywide
StatusPlanned

Data & Sources

Budget and project data: CCC Long Term Plan 2024–2034, orbviz.com capital programme API. Budget figures from CCC capital programme. Scope and status from official CCC communications and council agenda reports. Data as at March 2026.